At this project in Eindhoven, we installed several machines.
Two holes were drilled in the floor of the storey.
From the 4th floor, we worked with a hoisting gantry, combined with two electric chain hoists. This way we were able to lower the chain hoists straight down and create sufficient lifting height.
Then all the machines were lifted to the different floors. Once arrived at the floor, the floor was temporarily sealed in each case, so that the machines could then be transported on wheels to their final destination.
Everything thought out to the millimeter in advance and then executed accordingly.